Global Wind Power A/S
Jernbanegade 11
DK-7700 Thisted
Telefon +45 96 19 21 00
info@globalwindpower.com
bulgarien
 Long Man - Bulgaria
Global Wind Power is expanding in Bulgaria

As a rapidly growing company we are constantly on the lookout for new market opportunities. Global Wind Power believes in good wind and investments in Eastern Europe and consequently we have now entered the Bulgarian wind power market. Bulgaria is an exciting and potent wind power market and it is our intention to become a major player right from the beginning.

We are presently erecting our first project consisting of 5 Vestas V90 wind turbines outside Kavarna, just 56 kilometres from the city of Varna. With this project Global Wind Power is setting up the largest wind turbines ever in Bulgaria this year.

We started building the Long Man Wind Farm in July 2007 and it has been an incredibly interesting project all the way. As a new feature you can follow the project on this website.

             Wind measurement on site
0_-_fr_etablering_-_vindmlemast1 
             This picture shows the site prior to construction. It also
             shows a wind measurement mast collecting data for wind
             calculations
 
             Establishing foundations
1 -jordbundsforbedrende foranstaltninger
              Excavation for foundations has taken place and earth
              improvement measures have been made
2 - fundamentsgrube 
             The bottom has been stamped and compressed
3_-_fundamentsgrube_med_membran_-_fr_renselag
             The foundation pit has been covered with a plastic
             membrane and is now ready for casting the concrete deck 
  
4
              Casting of concrete deck
5
              Casting of concrete deck
6
              Foundation pit with completed concrete deck
8
              Foundation section placed on reinforcement
9
              Foundation section placed on reinforcement and further
              reinforcement measures can begin
7
             Here the foundation section has been reinforced and when
             it has been controlled, concreting can start
 
             Shipping  wind turbines from Denmark
10 
              5 Vestas V90 wind turbines have been shipped from Port 
              of Esbjerg at the end of October onboard the vessel  
               “M/V Polaris”
11 
              A wing measuring 44 meters in length is being lifted on
              board and afterwards welded on to the deck
12 
              A tower section is being lifted on board and afterwards
              welded on to the deck
13
              The nacelles, rotors and some of the tower sections are
              placed on the lower deck
14 
 
 
READ MORE